Cinemark

Cinemark 2017-06-26T18:20:05+00:00

Project Description

Parkway worked with Cinemark’s team to remodel its Oklahoma City location, which had been damaged by a severe storm.  Responding immediately, Parkway mobilized a team that succeeded in re-opening the 20-screen theater within eight days after significant roof damage and flooding. Parkway continued to renovate the entire theater while Cinemark remained open for guests.  This involved managing many complexities such as staging construction within an operating theater, coordinating the finishes with Cinemark’s design team and meeting the timeframes required by Cinemark.